Project to restore historic Brinsley Headstocks doubles in cost
The cost of replacing the historic Brinsley Headstocks has doubled because of unavoidable pressures, Broxtowe Council says.
Plans to replace the structure have been developed over the past couple of years but the project has faced delays.


The original wooden headstocks with parts dating from 1872 were dismantled and stored by the authority in December 2023 amid concerns that the structure was becoming unsafe.
In January 2025 the council approved a £220,000 full oak replacement expected to be installed by April 2026 although the wider site project had initially been due for completion in October 2025.
It included a new wildflower meadow and a remembrance orchard for miners who lost their lives at the pit.
At a cabinet meeting on September 29 councillors heard the cost had more than doubled to £453,000 while progress had been affected by several unforeseen challenges.
The council said savings had been made in forthcoming construction costs but pressures from site conditions programme delays and specialist construction requirements meant the budget would have to double.
An earlier delay followed the discovery of two old mining shafts in October 2024 after a ground investigation partly using old maps with one inaccessible tunnel beneath the planned orchard area.
Cabinet papers revealed a further significant setback after a third shaft covered by boards was discovered uncapped and unknown to the Mining Remediation Authority formerly the Coal Authority.
Coun Greg Marshall (Brox All) council deputy leader said the shaft must be capped to ensure the site was safe adding: “Nothing would be worse than a serious injury or indeed possible death associated with that site.”
Emma Georgiou interim director of environment and leisure said the council had approached the MRA about carrying out the capping work and would continue pressing it.
Zoe Rose-Higgins public safety and development director at the MRA said its inspection found the shaft securely fenced with no immediate public safety concerns and it had no record of a council funding request.
Groundworks were more complex because of buried rubble and obstructions while the French oak structure will be built off-site before work starts early next year for Easter 2027 completion.